How to change an activity

This can be done in 2 different ways, depending on what should be changed. If start- or end time should be changed, use Method 1. Otherwise use Method 2.

Method 1:

1. Mark the activity you want to change.
2. If the end time should be changed, mark the bottom line of the activity. The marker will then change to an arrow. The End time can be changed by holding down the left mouse key and drag & drop the end time of the activity to an earlier/later time (see How to move/copy an activity).
3. If the start time should be changed, mark the top line of the activity. The marker will then change to an arrow. Hold down the left mouse key and drag-and-drop the start time of the activity to an earlier/later time.
4. If start- and end- time should be changed, follow the steps 2 and 3.

Method 2:

1. Double click on the activity or right click with the right mouse key and select Open activity. The dialog for the selected activity is then displayed. Here you can change your desired parameters.

2. Press OK to save the changes.

Remember! If you use the Events-and activity tab, right click and select Open activity from the menu.